Moving Along






The house is completely bricked with stone and finishing touches are being made with the metal roof over porch outside of dining room. Inside is fully sheet-rocked and walls have been textured. Wood floor installation will begin this this week. Then the cabinets will be set, stone work inside will be completed, stairs installed and trim work will begin. We hope to see painting begin the first week of May and last 10 days or so. Following painting, ceramic tile walls and floors and granite will be installed. Plumbing, HVAC and Electric will begin around last week of May. House should be done in early June if all goes as planned!  